The FY2019 road paving project will begin on Monday May 6, 2019. To assist the Town in completing this project, we require no parking on the below streets and times. The road surface will first be removed (milling) followed by paving. This is a tentative schedule and may change due to weather events.
Monday May 6 - Mill - Tom Fox Ct, Gray Farm Ct, Conlon Ct & Hartz Pond Ct.
Tuesday May 7 - Pave - Tom fox Ct & Gray Farm Ct.
Mill - Hersperger
Wednesday May 8 - Pave Conlon Ct and Hartz Pond Ct,
Begin milling - Spurrier Ave, General Custer & Norris Rd.
Thursday May 9 - Finish Milling - Spurrier Ave, General Custer & Norris Rd,
Pave Hersperger Ln.
Friday May 17 - Pave - Norris
Monday May 20 - Pave - General Custer
Tuesday May 21 - Pave - Spurrier Ave.