The FY2019 road paving project will begin on Monday May 6, 2019. To assist the Town in completing this project, we require no parking on the below streets and times. The road surface will first be removed (milling) followed by paving. This is a tentative schedule and may change due to weather events.
Monday May 6 - Mill - Tom Fox Ct, Gray Farm Ct, Conlon Ct & Hartz Pond Ct.
Tuesday May 7 - Pave - Tom fox Ct & Gray Farm Ct.
Mill - Hersperger
Wednesday May 8 - Pave Conlon Ct and Hartz Pond Ct,
Begin milling - Spurrier Ave, General Custer & Norris Rd.
Thursday May 9 - Finish Milling - Spurrier Ave, General Custer & Norris Rd,
Pave Hersperger Ln.
Friday May 10 - Pave - General Custer,
Begin milling Hughes Gott, Luhn & Fletchall.
Monday May 13 - Finish milling Gott, Luhn & Fletchall,
Pave - Spurrier Ave
Tuesday May 14 - Pave - Norris and Luhn St.
Wednesday May 15 - Pave - Fetchall Rd.
Thursday May 16 - Pave Gott St.
Friday May 17 - Pave Hughes Rd.