This year's paving schedule will begin the week of September 8th. Several patches, sidewalk/trail repairs and the below listed streets will be done.
Westerly, Hoskinson (Bodmer to Tom Fox), Halmos, Hillard, Seymour Ct, Hoskinson Ct, Hackett Ct, Billek Ct and Milford Mill Rd.
The Town of Poolesville has awarded a contract for the 2014 paving program. Below is a tentative schedule and information regarding road access. Once the milling/paving crew is in your neighborhood, please keep parked cars off the roadway during construction.
The intersection of Westerly and West Willard will be completely rebuilt. During this phase of construction September 29 to October 1, the road will be closed to all traffic.
10/8 – 10/10 Asphalt patching work (Several Areas Throughout Town)
10/21 – Milling Crew on Westerly Avenue (West Willard Rd. to Hughes Rd.)
10/22 – Paving Crew on Westerly Avenue (West Willard Rd. to Hughes Rd.)
* Milling Crew Hoskinson Court,
* Milling Crew Hoskinson Road (Bodmer Ave. to Tom Fox Ave.)
* Milling Crew Halmos Park upper parking lot
10/23 – Paving Crew Hoskinson Court,
* Paving Crew Hoskinson Road (Bodmer Ave. to Tom Fox Ave.)
* Paving Crew Halmos Park upper parking lot
* Milling Crew Halmos Road
* Milling Crew Hillard Street (Hoskinson Rd. to Halmos Rd.)
* Milling Crew Seymour Ct. & Hillard Court
10/24 – Paving Crew Halmos Road
* Paving Crew Hillard Street (Hoskinson Rd. to Halmos Rd.)
* Paving Crew Seymour Ct. & Hillard Court
* Milling Crew Milford Mill Court
* Milling Crew Hackett Court
* Milling Crew Billek Court
10/27 – Paving Crew Milford Mill Court
* Paving Crew Hackett Court
* Paving Crew Billek Court
If you have any questions or concerns, please feel free to contact Town Hall.