The paving contractor has submitted the following schedule:
Milling & Paving Schedule
Friday August 26h – Move Milling machine to staging area (Stevens Park), post no parking signs on all streets to be milled and paved with appropriate dates on them
Wesmond Subdivision
Milling - Monday August 29th to Thursday September 1st
Paving - Tuesday August 30th to Friday September 2nd
Elizabeth's Delight
Milling - Friday September 2nd & Tuesday September 6th
Paving - Tuesday September 6th & Wednesday 7th
Wootton Heights
Milling - Wednesday September 7th to Friday September 9th
Paving - Thursday September 8th to Friday September 9th
All Cars must be removed from parking areas
Parking is permitted at Dr. Dillingham Park and along Wootton Avenue.
Schedule is tentative and could change by a day or so either way depending on productivity and unforeseen issues
This schedule is tentative and may change with weather conditions.