Kohlhoss Waterline Replacement Project Update
The Kohlhoss waterline project will resume on Wednesday, May 29, following the Memorial Day holiday. In addition, the Town received an updated schedule from the contactor, see below:
Water Main Replacement
5/14 to 5/29 Kohlhoss Rd from Wootton to 17551 Kohlhoss Rd
5/30 to 6/3 Wottoon Ave Court 19501 to 19523 Wootton
6/4 to 6/10 Kohlhoss Rd Court 17500 to 17534 Kohlhoss Rd Even
6/4 to 6/10 Kohlhoss Rd Court 17511 to 17545 Kohlhoss Rd Odd
6/11 to 6/13 Kohlhoss Rd Court 17549 to 17617 Kohlhoss Rd odd
7/12 to 7/22 Kohlhoss Rd From 17551 to Cattail Rd
7/23 to 7/30 Kohlhoss Rd Court from 17600 to 17650 Even
7/31 to 8/5 Kohlhoss Rd Court 17621 To 17661 Kohlhoss Rd Odd
8/6 to 8/24 Kohlhoss Rd Court 17665 to 17689 All
Service Connection replacement
6/6 to 6/7 Wottoon Ave Court 19501 to 19523 Wootton
6/28 to 7/5 Kohlhoss Rd Court 17500 to 17518 Kohlhoss Rd Even
6/26 to 6/27 Kohlhoss Rd Court 17511 to 17454 Kohlhoss Rd Odd
7/8 to 7/11 Kohlhoss Rd court 17549 to 17615 Kohlhoss Rd odd
8/19 To 8/26 Kohlhoss Rd Court from 17600 to 17650 Even
8/27 to 8/30 Kohlhoss Rd Court 17621 To 17661 Kohlhoss Rd Odd
9/2 to 9/10 Kohlhoss Rd Court 17665 to 17689 All
Paving will take place from 9/16 to 9/18